Rule 3
Information To Be Provided
–
Any person or corporate body who is interested to conduct survey, production, transmission or distribution of hydroelectricity of the capacity ranging from 100 to 1,000 kilo watt, shall
have to provide an information with the following particulars to the Secretary through the Electricity Development Department in the format as prescribed in Schedu1e-1 pursuant to the proviso clause of Section 3 of the Act :-
(a) Detail description of the project,
(b) Map of the project site (main structures must be shown),
(c) Source of water and quantity of water to be utilized,
(d) Area where the electricity is to be distributed and estimated number of consumers to be benefited from it,
(e) Whether the water resources to be utilized has already been utilized by other or not, if done so give the particulars of the same,
(f) Other necessary matters.
Any person or corporate body who is interested to conduct survey, production, transmission or distribution of hydroelectricity of the capacity ranging from 100 to 1,000 kilo watt, shall
have to provide an information with the following particulars to the Secretary through the Electricity Development Department in the format as prescribed in Schedu1e-1 pursuant to the proviso clause of Section 3 of the Act :-
(a) Detail description of the project,
(b) Map of the project site (main structures must be shown),
(c) Source of water and quantity of water to be utilized,
(d) Area where the electricity is to be distributed and estimated number of consumers to be benefited from it,
(e) Whether the water resources to be utilized has already been utilized by other or not, if done so give the particulars of the same,
(f) Other necessary matters.