Rule 3
Information To Be Provided

Any person or corporate body who is  interested to conduct survey, production, transmission or distribution of  hydroelectricity of the capacity ranging from 100 to 1,000 kilo watt, shall
have to provide an information with the following particulars to the  Secretary through the Electricity Development Department in the format as  prescribed in Schedu1e-1 pursuant to the proviso clause of Section 3 of the Act :-
(a) Detail description of the project,
(b) Map of the project site (main structures must be shown),
(c) Source of water and quantity of water to be utilized,
(d) Area where the electricity is to be distributed and estimated number of  consumers to be benefited from it,
(e) Whether the water resources to be utilized has already been utilized by  other or not, if done so give the particulars of the same,
(f) Other necessary matters.